I. Project No.:
Traffic 12
II. Project Location:
Northern Yongxing Industrial Park of New Airport District in Wenzhou City
III. Project Planning, Background and Construction Conditions:
The project, to be built on the land for construction, is indispensable to the New Airport District construction and aimed at optimizing the traffic infrastructures of the district and improving its economic development environment.
IV. Construction Scale, Content and Investment Estimation:
An investment of RMB 600 million (with funds for land use not included) will be needed for the construction of ①the municipal road engineering, which will be 13.25 km long and cover an area of 390,200 m2 , including the construction of roads, bridges, water supply and sewage pipelines, riverbank retaining walls, greening engineering and other auxiliaries ; ②the river course improvement and excavation engineering, which will be 2.66 km long and cover an area of 70,560 m2 , including earthexcavation, riverbank retaining walls, greening engineering and other auxiliaries (see the attached table).
V. Preparation and Progress:
At present, the project has been established and entered the construction documents design phase.
VI. Way of Cooperation:
BT (Build-transfer mode)
VII. Contact Details:
Unit to Contact:New Airport District Management Committee of Wenzhou City
Person to Conract:Huang Kewen
Tel:+086-577-89592020
Fax:+086-577-89592020
Add.: New Airport District Management Committee, Wenzhou City, Zhejiang, PRC
Postcode:325058
A Table of Municipal Engineering for Infrastructures in NorthernYongxingIndustrial Park
Name of Project
|
Project Briefing
|
|
|
River course improvement engineering of Weiyipu Road, Northern Yongxing Industrial Park
|
To excavate the river course with a length of 1226m and width of 40m, and construct green belts with a length of 15m and an area of 36,780 m2 on both banks of the river.
|
|
River course excavating engineering of Jingwupu Road, Northern Yongxing Industrial Park
|
To excavate the river course with a length of 1435m and width of 15m, and construct green belts with a length of 10m and an area of 28,700 m2 on both banks of the river.
|
|
Huancheng River course improvement engineering, Northern Yongxing Industrial Park
|
To excavate the river course with a length of 1622m and width of 40m, and construct a green belt with a width of 10m respectively on both banks of the river.
|
|
Municipal engineering of Jianshe Rd., Northern Section of Yongxing
|
To build a1194.845m long and 24m wide road,a bridge and a 120m long riverbank retaining wall.
|
|
Municipal engineering of Jingliu Access Rd., Northern Section of Yongxing
|
To build a 1348. 874m long and 24m wide road,a bridge and a 120m long riverbank retaining wall.
|
|
Municipal engineering of Jingwu Access Rd., Northern Section of Yongxing
|
To build a11975.147m long and 24m wide road,2 bridges and a 240m long riverbank retaining wall.
|
|
Municipal engineering of Weier Access Rd., Northern Section of Yongxing
|
To build a 1135.027m long and 18m wide road,a bridge and a 120m long riverbank retaining wall.
|
|
Municipal engineering of Weiyi Access Rd., Northern Section of Yongxing
|
To build a 1105.342m long and 40m wide road, a bridge and a 120m long riverbank retaining wall.
|
|
Municipal engineering of Weiyi Access Rd., Northern Section of Yongxing
|
To build a 1135.027m long and18m wide road,a bridge and a 120m long riverbank retaining wall.
|
|
Municipal engineering of Jingwu Access Rd., Northern Section of Yongxing
|
to build a 2100.385m long and 50m wide road, 2 bridges and a 240m long riverbank retaining wall.
|
|
Municipal engineering of Weier Access Rd., Northern Section of Yongxing
|
To build a 1086.006m long and 24m wide road,a bridge and a 120m long riverbank retaining wall.
|
|
Municipal engineering of Jingliu Rd., Northern Section of Yongxing
|
To build a 2212.253m long and 30m wide road, 2 bridges and a 240m long riverbank retaining wall.
|
|
|