  1.   Project No: 02

  2.   Name: The First Phase Project of Feiyunjiang River Third Bridge of Rui'an City

  3.   Location: Rui'an City

  4.   Background and Construction Condition:

  With the rapid development of the economy, the center of Rui'an City transfers to the eastern part. The original No.104 State Highway has turned out to be a road in the city, and become very busy. Thus, it is of great significance to build Feiyunjiang River Third Bridge to relieve the traffic pressure on the city, to ensure the clear transportation of No.204 State Highway, and to promote the cross-river extension of Rui'an City and the development of the north and south connection of the provincial level economic development zone. According to document No.130 [2000] of the Zhejiang provincial government, the Feiyunjiang River Third Bridge and its connection project is approved as “four-self highway project”of Zhejiang Province and has been regarded as one of the A type key projects of Ru'ian Municipal Government since 2003.

  The construction of the project started in April 2003 and now the investment has been 710 million yuan. 

  5.   Construction Scale and Target:

  With a total length of 18.1 km, including 11.6 km of the distance from the Feiyunjiang River Bridge (including the bridge) to the intersection of Dingtian Road on No.104 State Highway, the project is designed according to the class I highway standard. The roadbed is 33.5 m wide and the speed limit is 100 km/h. It links up in the south with the No.104 State Highway and No.56 Provincial Highway in Sunqiao petrol station. The temporary connection line will be constructed according to the standard of second-class highway. It is 6.52 km in length with a roadbed width of 18m and a designed speed limit of 80 km/h.

  The static investment is 902 million yuan. The investment recovery period: 9.3 years. Financial internal rate of return: 13.46%. The net present value: 1.789 billion yuan.

  6.   Cooperation Form and Content:

  Sole proprietorship or joint venture. Importation of capital and transfer of management right.

  7.   Conditions Provided by the Project Sponsor:

  Offering the information relevant to the project.

  8.   Sponsor Unit: Project Headquarters of Feiyunjiang River Third Bridge

  Person to Contact: Chen Qizhang

  Tel: 0086-577-65822811

  Fax: 0086-577-65822810   

  Postcode: 325200

  Add: 3rd Fl, the Auxiliary Building of the Bank of Construction, Ruian City

  E-mail: qizhang8088@126.com